The existing signal box had started to settle as a consequence of its age and that it was sitting on 15 metres of very soft ground. Due to the very restricted access around the structure, limited headroom restriction and that the works were close to ‘live’ tracks our small mini piling rig was utilised to install bottom driven mini piles.