144 No 220mm diameter bottom driven steel cased mini piles were installed to depths in the region of 10Lm though pre-excavated holes through an existing factory yard to support pilecaps on top of which a steel portal frame extension to the factory will be constructed. Three rigs were used to ensure the works were completed within three weeks.
on
in Case Studies
Industrial Factory Extension
Tags: commercial foundation, commercial piling, driven pile foundation, extension piles, foundation companies, foundation company, foundation contractors, Industrial and Commercial, industrial foundation, industrial piling, mini piling contractors, pile drilling, pile foundation, piling companies, piling company, piling contractors, piling specialists